Report 2010-102 Recommendation 19 Responses

Report 2010-102: Administrative Office of the Courts: The Statewide Case Management Project Faces Significant Challenges Due to Poor Project Management (Release Date: February 2011)

Recommendation #19 To: Administrative Office of the Courts

To ensure that any future IT projects are in the best interest of the judicial branch and the State, the AOC should document and retain all key decisions that impact the project in general, including the goals of the project.

1-Year Agency Response

The AOC indicates incorporating the Technology Agency’s recommendations into its existing processes, and using and retaining project concept documents, project charters, and other project planning documents more similar to those typically used for executive branch IT projects. (See 2013-406, p. 134)

California State Auditor's Assessment of 1-Year Status: Fully Implemented


All Recommendations in 2010-102

Agency responses received after June 2013 are posted verbatim.