Report 97116 Summary - March 1998

Health and Welfare Agency

:

Lockheed Martin Information Management Systems Failed To Deliver and the State Poorly Managed the Statewide Automated Child Support System

Results in Brief

In its contract with the State of California, Lockheed Martin Information Management Systems (Lockheed) promised to design, implement, and maintain the Statewide Automated Child Support System (SACSS). However, our review revealed that Lockheed did not fulfill its many promises to the State and failed to deliver a functional child support system. Specifically, we found that Lockheed did not deliver the project team it had promised, developed a flawed computer system that failed testing, and did not supply many of the deliverables promised in its contract with the State. Lockheed's failure to comply with the terms of its agreement contributed to the termination of the contract and a dysfunctional computer system.

Although we believe that Lockheed is responsible for many of the problems with SACSS, the State also contributed to the failure of SACSS because it did not take adequate action on quality assurance (QA) contractor warnings and mismanaged the administration of the project, thereby wasting millions of taxpayer dollars. From the planning to the installation phases of the project, the State made poor management decisions despite paying QA contractors $3 million for independent, impartial assessments of the project's methods, techniques, deliverables, and progress throughout the life of SACSS. Even though the contractors repeatedly warned the State about significant deficiencies in the project staffing and the system developed by Lockheed, the Department of Social Services (Social Services) and the Health and Welfare Agency Data Center (data center) failed to correct the problems and continued their efforts to install SACSS. Further, Social Services and the data center inappropriately increased the prices paid to Lockheed under the contract by more than $14 million. They also made inappropriate payments on the SACSS project in excess of $27 million, including payments for incomplete and inadequate deliverables.

The failure of SACSS cost taxpayers more than $111 million, and the State will pay up to another $11 million for Lockheed to maintain SACSS for those counties currently using the system. Additionally, Social Services estimates that the State now faces as much as $144 million over the next four years in potential federal penalties. The State also faces the challenge of beginning the project all over again while many children wait for child support payments from absent parents whom counties are unable to locate without help from a statewide automated system. In addition, recent welfare reforms increase the importance of improving child support collections because aid to families is limited under new laws.

A "Cascade of Events" Contributed to the System's Failure

SACSS did not fail as the result of one defect; rather, it was an accumulation of problems that caused the project to fail. When the airline industry investigates an accident involving a commercial airliner, it refers to the series of events that led to the accident as the "cascade of events." The cascade of events helps explain how a series of unrelated events or decisions formed a unique set of circumstances that led to the accident or failure. Similarly, we have examined the cascade of events that ultimately contributed to the failure of SACSS. The following is a summary of some of the more significant events that we believe contributed to the project's failure:

Recommendations

To avoid a repetition of the Statewide Automated Child Support System's (SACSS) failure, the Health and Welfare Agency should do the following:

In addition, the Legislature should memorialize Congress to amend federal laws governing child support enforcement automation efforts.

Agency Comments

The Health and Welfare Agency (State) generally agrees with our recommendations and with many of the audit findings regarding warning signs and project management issues. However, the State disagrees that its management decisions contributed to the failure of the project and that it allowed the counties to purchase personal computers and printers for SACSS prematurely.