Skip Repetitive Navigation Links
California State Auditor Logo  

Report Number: 2016-124

Abbreviations

Department of General Services and California Department of Technology
Neither Entity Has Provided the Oversight Necessary to Ensure That State Agencies Consistently Use the Competitive Bidding Process

Use the links below to skip to the chapter you wish to view:






Chapter 1
As a Result of Their Weak Oversight, General Services and Technology Lack Complete and Accurate Information About the State’s Contracts


Chapter Summary

Without complete and accurate information regarding its contracts, the State cannot ensure that agencies are engaging in competitive bidding when necessary and that the billions of dollars in annual procurements represent the best possible value. During the period from July 2011 through December 2015, General Services did not take the steps necessary to ensure that key stakeholders such as the Legislature had access to such comprehensive contracting data. Specifically, General Services implemented the State Contract and Procurement Registration System (SCPRS) in 2003 with the primary objective of providing a single repository for key information about state contracts that it could use to provide oversight and to demonstrate the visibility and accountability of state contracting activities. However, in part because of General Services’ failure to provide adequate guidance to the agencies that entered data into SCPRS, the database did not sufficiently serve the purposes for which General Services created it.

Although General Services transitioned from SCPRS to the new Financial Information System for California (FI$Cal) as its statewide contract database in January 2016, it is unclear when—and if—FI$Cal will fully solve the State’s lack of comprehensive contracting data. On one hand, after agencies begin to use FI$Cal for their procurements, the system automatically reports their contract data, reducing the likelihood of input error. However, less than a third of state agencies currently use FI$Cal, and those agencies that have not transitioned to the system generally must continue to manually enter contracting data within it, creating risk of errors. Finally, neither General Services nor Technology currently has formal plans to use FI$Cal to conduct analyses of statewide noncompetitive procurements to identify instances of abuse or misuse.

General Services Failed to Ensure That SCPRS Contained Complete and Accurate Information About the State’s Contracts

Partially in response to executive branch concerns, General Services created SCPRS in 2003 to serve as a repository for all the State’s contracting data. For more than 12 years, General Services required that the state agencies under its oversight enter their contracting information into SCPRS. Nonetheless, General Services did not ensure that SCPRS was accurate and met the State’s needs. As a result, SCPRS failed to serve many of the purposes for which General Services created it, leaving the State without a single repository of statewide contracts that it could monitor and analyze. When General Services transitioned to FI$Cal as its statewide contract database in January 2016, it essentially rendered SCPRS obsolete. However, as we discuss later in this chapter, the problems we identified with SCPRS may continue with FI$Cal unless General Services takes steps to resolve them.

In 2002 the Governor directed a three-member task force to review the State’s contracting and procurement procedures and make recommendations to ensure that state agencies used open and competitive bidding to the greatest extent possible and that their procurements received adequate oversight. The task force found that the State lacked a single system to track and capture contracting and procurement transactions. In fact, the task force pointed out that General Services could not even determine with certainty how much state agencies spent on contracts each year. The task force also found that General Services sometimes took weeks to compile questionable data when responding to legislative or public records requests because the State’s contracting and procurement information was located in numerous databases. As a result, the task force recommended that General Services implement an integrated system to track contract and procurement transactions that state agencies execute and to capture important data related to those transactions.

General Services’ Intended Purposes for SCPRS

  • Collect information about contracting and procurement activities that will allow the State to more effectively manage the contracting and procurement processes for which General Services is responsible.
  • Collect the appropriate type of contract and procurement information to assist General Services to perform its oversight functions.
  • Provide a single repository for key information about state contracts that can be sorted to provide timely and accurate information for state decision-makers, Public Records Act requests, and reports regarding contract‑related activities.
  • Collect information that will allow the State to demonstrate visibility and accountability over contract activities.

Source: General Services’ overview of SCPRS.

In response to the task force’s recommendation, General Services implemented SCPRS in 2003. General Services intended SCPRS to serve a number of purposes, as the text box shows. In concept, General Services—and starting in 2013, Technology—could have used SCPRS to determine the number and dollar value of the State’s noncompetitive contracts and to examine trends in agencies’ uses of such contracts. These analyses would have enabled the two oversight entities to better understand the scale of the State’s noncompetitive contracts and to identify situations in which agencies might be abusing noncompetitive contracts by favoring certain vendors. For example, General Services and Technology could have reviewed the value of noncompetitive contracts the State awarded to vendors over a time period and further investigated those cases where there appeared to be unusual trends.

However, we found the SCPRS data to be insufficient for these purposes. To gain some assurance of the accuracy and completeness of SCPRS, we tested a selection of 26 non-IT services contracts and their associated amendments of at least $1 million each that General Services approved from July 2011 through December 2015. We also examined the SCPRS data for an additional five contracts and associated amendments, including contracts for non-IT goods and services and IT services, from this same period. Our review found that SCPRS contained inaccurate information and did not include a number of contracts and associated amendments. As a result of SCPRS’ incomplete and inaccurate data, stakeholders such as the Legislature cannot rely on the database to better inform their decision-making about the State’s noncompetitive contracts. Further, its inaccurate data undermined the purposes for which General Services created it and rendered it essentially useless in addressing the task force’s original concerns.

Many of the errors we found resulted from agencies entering data into the database incorrectly. SCPRS relied upon the state agencies to manually enter information about their contracts. However, our findings suggest that some agencies did not understand how to correctly enter this information. For example, the SCPRS data misrepresented nine of the 31 contracts and associated amendments we reviewed as competitively bid when, in fact, they were not competitively bid. In five of these cases, the agencies recorded a single SCPRS entry that combined the total dollar amount of a competitively bid contract and its noncompetitive amendments. Despite the noncompetitive amendments, SCPRS lists the entire entry as being competitively bid. Figure 3 shows an example of this type of error. In this instance, the original, competitively bid contract for DMV to acquire terminals was for about $3 million. DMV subsequently amended its original contract nine times, without competition, which added an additional $31 million to the cost of the contract. Nonetheless, SCPRS listed a single, competitively bid contract for $34 million. This error effectively obscured the true acquisition method that General Services is charged with limiting.

We also found that 12 of the 31 contracts and amendments we reviewed were missing from SCPRS because agencies had failed to enter them. Although General Services required agencies to report all contracts over $5,000 into SCPRS, we identified a number of high‑value contracts that the database did not include. As we show in the second example in Figure 3, one of the contracts identified as missing from SCPRS included eight amendments and was worth $163 million. This contract between the Department of Developmental Services and San Gabriel/Pomona Valleys Developmental Services was for services to people with developmental disabilities. These missing contracts illustrate the profound limitations of SCPRS as a source of data to demonstrate transparency and accountability in contracting activities.

Figure 3
Two Examples Demonstrate How the SCPRS Data Misrepresent Noncompetitive Procurements

Two examples of errors demonstrate how the SCPRS data misrepresent noncompetitive procurements.

Source: California State Auditor’s analysis of SCPRS.

Note: The contracts were either amended using the noncompetitive request process or were exempt from competition through another policy or statute.

The errors we noted were likely due to General Services’ failure to implement sufficient controls to ensure the data’s accuracy and completeness. For example, although General Services employed various methods to guide and monitor agencies’ entry of data into SCPRS, it did not ensure that agencies had sufficient technical instructions for how to enter information about amendments. Specifically, the technical user instructions created by the vendor that maintained SCPRS did not clarify that agencies should enter amendments as separate line items in the database. Although it was aware of this problem, General Services did not issue sufficient technical instructions to resolve it. According to a section manager in General Services’ Procurement Division, because the Department of Finance issued a 2008 budget letter that announced a moratorium on developing or upgrading any systems that would duplicate the functionality of the FI$Cal project, General Services intended to retire SCPRS soon after the budget letter and so did not prioritize issuing guidance on this issue. She further stated that General Services could obtain accurate contract information from individual agencies. However, notifying agencies on how to properly enter amendments into SCPRS would not have been a development or upgrade to the database. In addition, because General Services did not issue sufficient guidance on this topic during the nearly eight years between the budget letter and its transition to FI$Cal in January 2016, it ultimately rendered SCPRS useless for the purpose of serving as a single repository for accurate information about the State’s contracts.

Similarly, General Services did not adequately instruct agencies to report all required contracts in SCPRS. When we asked General Services about the missing contracts we identified, a section manager stated that agencies were sometimes unclear about which contracts they needed to report into SCPRS. Specifically, agencies sometimes assumed that they did not need to report contracts that were exempt from competitive bidding. Although the Governor issued an executive order in 2011 requiring agencies under his direct authority to provide General Services with as much contracting information as possible, General Services did not issue sufficient guidance between 2011 and 2015 reiterating the need for agencies to report all contracts into SCPRS, including contracts exempt from competitive bidding. Consequently, General Services did not adequately ensure that the SCPRS data were as complete as possible.

In addition, General Services did not formally examine the accuracy of agencies’ entries when it performed audits of agencies under its oversight. During our audit period, General Services’ Office of Audit Services (Audit Services) reviewed agency compliance with the State’s contracting policies, including verifying that the agencies entered required contracts in SCPRS. However, Audit Services had no written procedures for its staff to regularly verify the accuracy of the data the agencies entered. Because some of the contracts we tested in SCPRS had incorrectly recorded dollar amounts, numbers of amendments, and acquisition methods, we believe Audit Services should have done more to monitor those entries into SCPRS, such as establishing procedures to review these important data fields. Instead, Audit Services missed an opportunity to ensure the integrity of the SCPRS data and educate agencies on the appropriate method of entering contracting information. The acting chief of Audit Services stated that his staff would create procedures to review the accuracy of FI$Cal entries in the future.

Because of these severe limitations in SCPRS’ accuracy and completeness, we could not use it to accurately determine the number and value of noncompetitive contracts General Services or Technology approved during our audit period as the Legislature requested. Therefore, we attempted to use General Services’ and Technology’s internal databases or other data sources to capture the relevant data. General Services’ and Technology’s various units use these internal data sources when approving different types of contracts for workload tracking purposes, such as assigning tasks to staff. However, as Figure 4 shows, these data sources do not capture the complete picture of the State’s contracts either. For example, we could not use two of the five data sources because they do not clearly distinguish between competitive and noncompetitive contracts and contain inconsistent dollar amounts. Further, the other three data sources contain incorrect dollar amounts, list incorrect procurement methods, or are incomplete.

Notwithstanding our concerns with these data sources, we used them to attempt to determine the number and dollar value of competitive and noncompetitive contracts and amendments that General Services and Technology approved because their data were the best available. Using these data, we estimate that the State awarded at least $44 billion in noncompetitive contracts over $1 million from fiscal year 2011–12 through fiscal year 2015–16. General Services asserts that noncompetitive requests accounted for only $3.2 billion of this total. Although we have concerns with the integrity of the data, we used some of this information in an attempt to verify General Services’ assertion, but we arrived at a figure of about $5 billion. This discrepancy underscores the importance of having a single repository of sufficiently reliable data. The noncompetitive category also contains non‑IT services contracts using other exemptions from competition, such as interagency and local assistance contracts between public entities. Regardless of the various components included in noncompetitive spending, the sheer magnitude of the value of the State’s noncompetitive contracts during this period emphasizes the importance of ensuring that the State provides adequate oversight of agencies’ contracting practices.

Figure 4
General Services’ and Technology’s Databases Are Inadequate for Accurately Identifying Contracts Over $1 Million
  Fiscal Years 2011–12 Through 2015–16

Figure 4 describes why General Services’ and Technology’s databases are inadequate for accurately identifying contracts over $1 million fiscal years 2011-12 through 2016-16.

Sources: California State Auditor’s analysis of General Services’ internal tracking procurement databases and logs and Technology’s internal tracking procurement database.

Note: According to General Services and Technology, these respective databases are intended for workflow planning and not for external reporting.

* General Services asserts that noncompetitive requests account for only $3.2 billion of this total. Although we have concerns with the integrity of the data, we used some of this information in an attempt to verify General Services’ assertion but arrived at a figure of roughly $5 billion for these noncompetitive requests. This discrepancy underscores the importance of having a single repository of sufficiently reliable data. The noncompetitive category also contains non-IT services contracts using other exemptions from competition, such as interagency contracts between public entities and contracts providing assistance to local governments to aid the public directly.

The other category contains contracts with an unknown procurement method. According to General Services, staff may choose this other category for either a competitive or noncompetitive procurement. General Services stated that because its internal databases are only intended for workflow tracking, it did not go back to determine if staff could have recorded a more specific procurement method.

Although General Services Recently Transitioned to FI$Cal as Its Statewide Contract Database, It Is Unclear When and to What Degree the Data on State Contracts Will Improve

In January 2016, General Services transitioned from SCPRS to FI$Cal as its statewide contract database. As a legislatively mandated project, the Legislature’s objectives for FI$Cal’s procurement functions are similar to General Services’ previous objectives for SCPRS: they include maintaining a central source of procurement data, supporting better decision making through the use of standardized data and procurement management reports, and improving access to and the transparency of the State’s procurements. FI$Cal has the potential to significantly improve the State’s contracting data because it serves not just as a database but can also be used by agencies to make procurements. As a result, after agencies transition to FI$Cal, the system automatically reports their contract data, reducing the likelihood of input errors. Nonetheless, it is unclear when and even if all state agencies will begin using FI$Cal for their procurements. Those that do not use FI$Cal for their procurements generally must continue to manually enter their contracting information into the system. Consequently, the problems we identified with SCPRS may persist with FI$Cal unless General Services takes steps to resolve them.

FI$Cal data should be more consistent than SCPRS data but only for agencies using FI$Cal’s automatic procurement reporting function. As Figure 5 illustrates, under SCPRS, state agencies engaged in two steps: procuring goods and services and then manually reporting that procurement in SCPRS. As we previously discussed, some agencies’ manual entry led to significant errors in the data. In contrast, according to FI$Cal and General Services documents, agencies that have transitioned to FI$Cal use it to procure goods and services, and the system automatically collects and reports that information, thus eliminating the need for the users to separately report their procurements. Therefore, FI$Cal’s data should be more consistent than SCPRS’ data for those agencies that transition to the new system. However, any agencies that are not yet using FI$Cal for their procurements—because they are scheduled to use the system in the future, they have deferred transitioning to the new system, or they are not required to use it—generally must continue to manually report contract information into the system.

At this time, less than a third of state agencies are using FI$Cal, and a significant number of the remaining agencies are not scheduled to begin using it in the near future. According to General Services, 57 agencies currently use FI$Cal for their procurements, or about 31 percent of the total number of entities currently scheduled to use it. FI$Cal’s implementation plan states the remaining state agencies should begin using the system by July 2018. However, based on our office’s January 2017 letter report on the implementation of FI$Cal, we believe that FI$Cal may find it necessary to extend the July 2018 deadline because of its scheduling challenges. Additionally, according to FI$Cal documents, 19 entities are currently deferred or exempt from using FI$Cal, including some large agencies such as the California Department of Transportation and the California Department of Corrections and Rehabilitation. According to FI$Cal’s implementation plan, agencies that have deferred their transition to FI$Cal should begin to use it when their own business management systems become obsolete. On the other hand, agencies that state law exempts from using FI$Cal may never transition to it. However, the Legislature intends for these agencies to either eventually use FI$Cal or create an interface between their own systems and FI$Cal.

Figure 5
Unlike SCPRS, FI$Cal Automatically Reports Contract Information When Agencies Use It to Make Procurements

Figure 5 is a comparison that outlines the differences between data input in SCPRS and FI$Cal when procurement for goods and services are made.

Sources: General Services management memos, State Contracting Manual, FI$Cal training documents, FI$Cal’s sixth special project report, and the California State Auditor’s FI$Cal status letter published in January 2017.

* Deferred state agencies are intended to use FI$Cal when their own business management systems become obsolete. Exempt state agencies have a statutory provision allowing them to not use FI$Cal.

The low number of agencies using the automated reporting feature of FI$Cal calls into question when and to what degree the State’s contracting information will become more reliable and complete. Because a large number of agencies do not currently use FI$Cal to procure goods and services, General Services needs to ensure that those entities under its oversight accurately enter all required contract information into the system. General Services employs some methods of ensuring that the agencies that have not yet transitioned to FI$Cal still report accurate and complete information into the database; for instance, it created a spreadsheet to assist agencies not using FI$Cal to submit large numbers of contract entries into the system. However, we noted concerns with how General Services monitored these agencies entering contracts into the system, which may not adequately ensure FI$Cal’s current integrity.

Specifically, General Services’ Audit Services has not verified the accuracy and completeness of the procurement data in FI$Cal since the transition from SCPRS more than a year ago, in January 2016. The acting chief of Audit Services stated that because of FI$Cal’s complexity and General Services’ resource constraints, his office has only performed a cursory review of whether agencies reported contracts into the system, rather than formally reviewing whether manual reporting agencies entered contracts and did so accurately. Although we acknowledge that becoming familiar with FI$Cal may take time, Audit Services could have compared contracts it obtained during its review to the information entered in FI$Cal. Instead, General Services missed an opportunity to evaluate how agencies are reporting contracts into the new system.

Starting in April 2017, General Services’ Purchasing Authority unit began selecting a sample of procurements from agencies with delegated purchasing authority and ensuring that the agencies reported the procurements accurately into FI$Cal. The section manager in the Purchasing Authority unit stated this process should be more robust than Audit Services’ previous process for ensuring the reliability of the SCPRS data. Thus far, General Services’ Purchasing Authority unit has verified a selection for six agencies’ contracts in FI$Cal and noted several errors. The section manager asserted that once General Services completes its reviews, it will document the findings and seek corrective action for areas of noncompliance.

Furthermore, FI$Cal’s structure may currently prevent General Services and Technology from accurately identifying the State’s spending on amendments. Although FI$Cal allows agencies to identify whether goods and services were noncompetitively procured, it does not currently allow agencies—whether or not they use FI$Cal to procure their goods or services—to clearly indicate that procurements were made using amendments. Agencies using FI$Cal for procurements can identify amendments by entering either text or numeric descriptions. However, because both options are permissible, General Services and Technology may find inconsistent information in FI$Cal. For example, one agency may indicate an amendment by writing “Adding $5 million for additional services,” while another agency may describe the amendment as “A07.” On the other hand, agencies that do not use FI$Cal to procure goods and services must identify their entries as an amendment by selecting the other category, which can capture items besides amendments. According to the section manager in the Procurement Division, these agencies will also identify their FI$Cal entries as amendments by writing text or a numeric description. This lack of consistency in FI$Cal’s data will impede General Services’ and Technologys’ ability to accurately analyze the State’s noncompetitive spending on amendments at an aggregate level.

General Services has the ability to request that FI$Cal modify certain aspects of the system’s procurement component, including adding a clear, standardized indicator for amendments. When we asked why General Services had not made such a modification, the section manager in the Procurement Division stated that General Services wished to assess how FI$Cal was currently working for agencies before modifying it. However, we believe that a standardized amendment indicator is necessary in order for General Services to properly oversee the State’s amended contracts. Such an indicator would allow it to identify the number and value of the amendments that agencies have awarded noncompetitively and to examine patterns of agencies that are overusing or inappropriately using the noncompetitive process through their amendments. Further, General Services should not have waited for agencies to use FI$Cal for more than a year without making this modification, as the delay further jeopardizes the data’s integrity. General Services agreed that an amendment indicator would likely improve the accuracy of its analyses and reporting, and in May 2017 it requested that FI$Cal modify the system to include an amendment indicator.

General Services and Technology Have Not Established Plans to Conduct Statewide Analyses of the State’s Noncompetitive Contracting Practices

Based on SCPRS’ intended purposes, on the Legislature’s intent in enacting the Public Contract Code, and on the fact that state law requires General Services to oversee and improve the State’s contracting practices, we expected General Services to have ensured the accuracy of the SCPRS data and then used those data to perform statewide analyses in order to improve its oversight. In addition, because state law generally requires Technology to oversee the State’s contracts for reportable IT projects and telecommunications goods and services, we expected Technology to also have performed statewide analyses of procurements it oversees. Examples of such analyses include examining the proportion of the State’s competitive and noncompetitive spending and identifying trends in the State’s noncompetitive procurements over time. However, as we previously discussed, General Services did not ensure that SCPRS’ data were sufficient for the purposes of performing these analyses. As a result, General Services and, subsequent to 2013, Technology were limited in their ability to oversee the State’s noncompetitive contracts by, for example, detecting and preventing abuse or favoritism.

Although the State transitioned to FI$Cal as its statewide contract database over a year ago, we are concerned that General Services and Technology still do not have formal plans to conduct regular statewide analyses using the FI$Cal data. Because there are no plans to monitor noncompetitive contracts using statewide data, General Services and Technology are not upholding their responsibility to protect the State’s interests. Table 4 identifies examples of statewide analyses of noncompetitive procurement that we believe General Services and Technology should perform. When we asked why General Services and Technology did not have plans to perform these types of analyses, the entities indicated they had prioritized becoming familiar with the complexities of FI$Cal. Although we understand this is important, we believe General Services and Technology could have created preliminary plans for performing statewide noncompetitive analyses and updated those plans as more agencies began using the system. General Services and Technology agreed that statewide analyses are important and indicated they would start developing plans to conduct such analyses in the near future.

Table 4
General Services and Technology Could Use FI$Cal Data to Analyze the State’s Noncompetitive Procurements

Type of Statewide Analysis Purpose That the Analysis May Serve Necessary Information to Perform Analysis
Calculate the total dollar value and number of all state contracts and amendments. Informational: demonstrate the significance of state spending on contracts and amendments. Number and dollar value of contracts and amendments.
Calculate the proportion of the number and value of contracts and amendments awarded noncompetitively. Track the extent to which state agencies use competitive contracting practices. Procurement method, number, and dollar value of contracts and amendments.
Identify trends in agencies’ uses of noncompetitive contracts and amendments, such as increases or decreases over time. Identify areas where the State may be overusing or abusing noncompetitive contracting practices. Agency name, procurement method, number and dollar value of noncompetitive contracts and amendments.
Calculate the total number and dollar value of noncompetitive contracts and amendments awarded to particular vendors. Determine if certain vendors are more likely to be awarded noncompetitive contracts and amendments or are receiving higher prices for similar work over time. Vendor name, procurement method, number and dollar value of noncompetitive contracts and amendments.
Identify trends in agencies’ use of amendments resulting from a noncompetitive request that were added to originally competitively bid contracts. Ensure that agencies are not using amendments to abuse noncompetitive requests. Amendment indicator, procurement method, contract identifier, number and dollar value of amendments.
Compare noncompetitive contract and amendment amounts to agencies’ purchasing thresholds. Identify instances in which agencies may be splitting noncompetitive contracts and amendments to avoid complying with approval authority or delegated purchasing thresholds. Agency name, purchasing thresholds, procurement method, number and dollar value of contracts and amendments.

Sources: California State Auditor’s analysis of National Association of State Procurement Officials publications, Public Contracting Code, and Association of Government Accountants publications.

Note: FI$Cal currently does not allow agencies to clearly indicate that procurements were made using an amendment.

Recommendations

General Services

To improve its oversight of the State’s noncompetitive contracts, General Services should take the following actions:

Technology

To improve its oversight of the State’s noncompetitive contracting related to reportable IT projects and telecommunication procurements, Technology should create plans within 90 days for regularly performing statewide analyses of FI$Cal data to identify potential abuse or overuse of noncompetitive contracts. These analyses should include, but not be limited to, calculating the proportional value and number of the State’s competitive and noncompetitive contracts and amendments, examining trends in agencies’ use of noncompetitive contracts and amendments, and identifying unusual patterns among vendors receiving state contracts through noncompetitive means.




Back to top




Chapter 2
General Services and Technology Have Not Always Ensured That Agencies Competitively Award Contracts When Appropriate

Chapter Summary

General Services and Technology have not ensured that state agencies avoid or minimize their use of noncompetitive requests. As the Introduction describes, noncompetitive requests for non-IT goods and IT goods and services acquisitions allow state agencies to apply to bypass the competitive process for procurements when only one vendor can provide a needed good and service. For non-IT services acquisitions, state agencies fill out noncompetitive requests to explain why they are affording a single business enterprise the opportunity to provide the specified services. General Services uses this information to determine whether the noncompetitive requests are properly justified and in the State’s best interest. However, when we reviewed 27 noncompetitive requests that General Services and Technology had approved, we found that nine—with a combined value of nearly $1 billion—lacked adequate justification for bypassing the competitive bid process. In each of these nine instances, the state agency generally could have avoided using a noncompetitive request if it had engaged in sufficient planning. Further, General Services and Technology approved 14 of the 27 noncompetitive requests even though the agencies had not adequately substantiated that the vendors’ prices were fair and reasonable, as the noncompetitive request form requires. Finally, although state law gives both General Services and Technology the authority to use a number of enforcement mechanisms, both entities rarely employed these mechanisms to ensure that agencies only used the noncompetitive request process when appropriate. As a result, the State may have limited competition and failed to receive the best value in its procurements.

By Allowing Agencies to Inappropriately Bypass the Competitive Process, General Services and Technology Have Limited Competition

Our review found that both General Services and Technology approved noncompetitive requests for contracts that agencies could have awarded competitively, calling into question whether the State has limited competition and thus may have needlessly paid more or received lower-quality goods and services. Both oversight entities have the ability to deny agencies’ noncompetitive requests if those requests fail to meet applicable criteria. Nonetheless, when we tested 27 noncompetitive requests that General Services and Technology approved, we found that the agencies could have competitively awarded nine of these procurements, which had a total value of nearly $1 billion.

As shown in Table 5, General Services approved five of these noncompetitive requests, and Technology approved the other four. Moreover, General Services and Technology approved 14 of the 27 noncompetitive requests that we reviewed even though the agencies did not adequately justify the prices of the contracts. In fact, our review demonstrates that in one instance, the prices in the contract were higher than the prices that the same vendor charged the State for similar services in other agreements. The fact that General Services and Technology approved these noncompetitive requests despite the lack of adequate price justification leads us to question whether these entities are providing the level of oversight necessary to protect the State’s best interests.

Both General Services and Technology Approved Noncompetitive Requests That Did Not Meet Applicable Criteria

General Services’ Key Criteria for Assessing the Appropriateness of Noncompetitive Requests

  1. The agency submitted the noncompetitive request to General Services for review more than 45 days before it needed approval for the contract or amendment.
  2. The agency adequately demonstrated that the procurement was restricted to the good, service, or supplier.
  3. The agency adequately demonstrated that it conducted market research to substantiate that no competition existed.
  4. The agency adequately demonstrated the consequences of not purchasing the good or service or contracting with the proposed supplier.
  5. The agency adequately demonstrated that the price was fair and reasonable.
  6. The agency adequately demonstrated that the procurement would result in cost savings or averted costs for the State.

Sources: General Services’ policies and questions contained in the noncompetitive request application form.

According to the State Contracting Manual, state agencies can only use noncompetitive requests for non-IT goods or IT goods and services when a proposed acquisition is the only good and service that meets the State’s needs. For non-IT services acquisitions, state agencies fill out noncompetitive requests to explain why they afforded only a single business enterprise the opportunity to provide the specified services. General Services uses this information to determine whether noncompetitive requests are in the State’s best interests by verifying they meet the key criteria in the text box. Agencies may use noncompetitive requests for both original contracts and amendments. The State Contracting Manual generally requires an agency to submit a noncompetitive request to change the terms of the contract and its competitive solicitation. For example, an agency must submit a noncompetitive request if it wishes to add unanticipated funds or services to the contract.

General Services created a two‑page justification form agencies fill out for their noncompetitive requests. Both General Services and Technology use this form, which requires agencies to substantiate why their noncompetitive procurements are unique and to show that they conducted the appropriate level of market research to substantiate the lack of available vendors. Further, the form requires the agencies to describe the consequences of not purchasing the proposed goods or services so that General Services and Technology can determine, in part, whether the noncompetitive request is in the State’s best interest. Finally, the form requires agencies to justify that the vendors’ prices are fair and reasonable and describe any cost savings realized or costs avoided by acquiring goods or services through the specific vendors.

Table 5
General Services and Technology Approved Noncompetitive Requests for Contracts That Could Have Been Competitively Bid
(in Millions)

Contracting Agency Name Reason for Noncompetitive Request Contract or Amendment Original Contract’s Dollar Value Total Dollar Value Before Amendment Dollar Value of contract or amendment we evaluated Percentage Increase Related to Amendment
General Services' Oversight Health Care Services Extension and increase of cost for Medi-Cal dental program contract. Seventh Amendment $7,779 $7,777* $835 11%
DMV Extension and increase of cost for updating the driver’s license card production system currently experiencing technical issues. Fifth Amendment 62.8 68.4 75.5 110
High-Speed Rail Extension and increase of cost for financial consulting services. Second Amendment 2.5 5.8 3 52
Department of Forestry and Fire Protection Extension and increase of cost for Cal Fire aviation services. Fourth Amendment 137.8 153.2 27.8 18
CPUC Extension and increase of cost for California Lifeline program. Sixth Amendment 36.1 63.4 6.9 11
Technology's Oversight Department of Fish and Wildlife Continued maintenance and operations for automated licensing system. Original Contract $28.9 NA $28.9 NA
EDD Extension and increase of cost for additional vendor staff to support the unemployment benefits system. Needed vendor staff because EDD staff was not trained to carry out vendor’s responsibilities. Fourth Amendment 0.6 8 2 25%
DMV Extension and increase of cost for more self‑service terminals. Ninth Amendment 2.7 15.2 18.6 122
Secretary of State Extension of project management services for the statewide voter database. Original Contract 2.3 NA 2.3 NA

Sources: California State Auditor’s analysis of General Services’ and Technology’s procurement files.

Note: The results are based on the criteria that General Services uses and Technology follows to assess the appropriateness of noncompetitive requests. Noncompetitive requests appear in the table if the requesting agency did not substantiate that it met certain criteria. 

NA = Not applicable.

* The value of the contract before our test item was less than the original contract amount because Health Care Services had a prior amendment that adjusted the contract value.

Similar to an amendment, these contracts continue services with the same vendor but under a new contract.

We used the criteria shown in the text box to determine whether the 27 noncompetitive requests that we analyzed included adequate justification on the form. We found that in some instances, noncompetitive requests enabled the State to appropriately procure goods and services. For example, Technology approved a noncompetitive request from the Office of Emergency Services for a $2.7 million contract for a vendor to provide a software service that transferred emergency 9-1-1 text messages between public safety call centers and collected statistics on those texts. In its noncompetitive request, the agency cited that this vendor was currently the only one that held contracts with the two companies that provide text services across the country, allowing for the transfer of emergency texts between public safety call centers. Further, the agency stated that this vendor alone could provide its proprietary technology for collecting statistics on those texts. It justified its request by providing a proprietary technology letter and summarizing the results of its market research. In this example, we believe that the agency adequately justified that only one vendor could meet the State’s needs. However, General Services and Technology approved nine other noncompetitive requests that did not meet key criteria in the form that General Services itself established and that Technology follows, as Table 6 demonstrates. We discuss a number of these noncompetitive requests in greater detail in the following sections.

General Services and Technology Approved Noncompetitive Requests That Were Largely the Result of Agencies’ Failure to Sufficiently Plan

Our review determined that General Services and Technology approved nine noncompetitive requests that agencies could have avoided if they had engaged in sufficient planning. These agencies generally did not ensure that they had time to solicit information or bids to identify if other potential vendors could meet their needs before their contracts for critical services expired. General Services and Technology generally approved these noncompetitive requests because they determined that immediate acquisitions were necessary to avoid disrupting essential State services. However, the agencies did not demonstrate that they sufficiently planned to avoid these situations, which might have prevented the urgent need for these procurements. Although the State Contracting Manual states, for other than non-IT services, that poor planning is not an emergency, it fails to define what constitutes poor planning. Further, the section of the State Contracting Manual that covers non‑IT services acquisitions fails to mention that poor planning is not an emergency. This is particularly important to highlight given that this section of the manual does not provide specific language for what constitutes an allowable noncompetitive request for non-IT services. By not providing enough guidance regarding this issue in the State Contracting Manual, General Services may have contributed to agencies’ use of inappropriate noncompetitive requests.

Table 6
General Services and Technology Approved Noncompetitive Requests That Did Not Meet Key Criteria
(in Millions)

Contracting Agency Name Reason for Noncompetitive Request Contract or Amendment Dollar Value of Contract or amendment we evaluated Did Agency Provide Sufficient Justification That the acquisition was restricted to the good, service, or supplier?* Did Agency Sufficiently Plan for Procurement?* Did Oversight Entity Assert That This Acquisition Affected essential state services?
General Services' Oversight Health Care Services Extension and increase of cost for Medi-Cal dental program contract. Seventh Amendment $835 X X
DMV Extension and increase of cost for updating the driver’s license card production system currently experiencing technical issues. Fifth Amendment 75.5 X X
High-Speed Rail Extension and increase of cost for financial consulting services. Second Amendment 3 X X
Department of Forestry and Fire Protection Extension and increase of cost for Cal Fire aviation services. Fourth Amendment 27.8 X X
CPUC Extension and increase of cost for California Lifeline program. Sixth Amendment 6.9 X X
Technology's Oversight Department of Fish and Wildlife Extension and increase of cost for continued maintenance and operations for automated licensing software system. Original Contract $28.9 X X
EDD Extension and increase of cost for additional needs/staff to support the unemployment benefits system. Needed vendor staff because EDD staff was not trained to carry out vendor’s responsibilities. Fourth Amendment 2 X X
DMV Extension and increase of cost for more self‑service terminals. Ninth Amendment 18.6 X X X
Secretary of State Extension of project management services for the statewide voter database. Original Contract 2.3 X X

Sources: California State Auditor’s analysis of General Services’ and Technology’s procurement files.

= Met the requirement.

X = Did not meet the requirement.

* We primarily used these two factors when determining whether a noncompetitive request could have been avoided. We determined that an agency did not sufficiently plan by evaluating factors such as whether the agency submitted the noncompetitive request close to the existing contract’s expiration date or the agency cited insufficient time to do a competitive solicitation. Further, we determined whether the agency demonstrated that it performed market research to substantiate there was no existing competition.

Similar to an amendment, these contracts continue services with the same vendor but under a new contract.

In one example that illustrates insufficient planning, the California Public Utilities Commission (CPUC) requested a sixth amendment in 2016 to its contract with its current vendor for providing administration services related to reimbursing telephone service providers for the State’s discounted communication program for low-income households. The CPUC initially entered into this contract in 2011 for $36 million. The first four amendments added a total of $2.2 million to the contract’s price. The CPUC then submitted a noncompetitive request for a fifth amendment adding $25 million and one year to this contract in 2015, 37 days before the contract’s expiration, despite General Service’s 45‑day requirement for reviewing noncompetitive requests. In its noncompetitive request, which General Services approved, the CPUC stated that it would prepare a request for proposal as soon as possible to begin the competitive bidding process, which could take 18‑24 months. However, instead of doing so, the CPUC submitted a noncompetitive request in 2016 for a sixth amendment that would extend the contract by a year and add an additional $6.9 million to the existing $63 million contract. In this noncompetitive request, the CPUC stated that an immediate acquisition was justified because otherwise more than two million low-income Californians would be at risk of losing discounted communication services, the State would not meet statutory requirements, and the CPUC would be subject to significant litigation and potential financial penalties. The CPUC submitted this noncompetitive request to General Services just 34 days before the existing contract was set to expire. In other words, twice the CPUC created the urgent situation by submitting its noncompetitive request so close to the contract’s expiration date.

Nonetheless, rather than using any of the formal enforcement mechanisms at its disposal—which we discuss later in this chapter—General Services approved the request, citing the complexity and importance of this public assistance program and stating that the extension allowed time for the CPUC to prepare a request for proposal before the contract expired. Given the CPUC’s failure to follow through with a competitive process following its fifth amendment, we question General Services’ decision not to monitor the agency or take enforcement action to ensure that it was demonstrating progress in initiating a competitive bidding process. Moreover, near the end of our audit we learned that General Services approved a seventh amendment to the contract which added nearly $14 million and extended the contract term by 11 months. In its noncompetitive request, CPUC once again cited the need for additional time to competitively award the contract.

Similarly, General Services approved High-Speed Rail’s noncompetitive request for an amendment that extended the term of a contract by one year and increased its costs from $5.8 million to $8.8 million. Specifically, in 2013, General Services approved High-Speed Rail’s $3 million noncompetitive request for a second contract amendment for financial consulting services. High-Speed Rail submitted this noncompetitive request just 17 days before the expiration date of the existing contract, stating that the financial consulting services were critical to its mission and that the financial consultant’s skills were “specialized and not widely available.” However, this assertion does not justify why this vendor alone could meet the State’s needs because High-Speed Rail indicated that three other firms had responded to the original solicitation—two of which had submitted bids that had scores close to the chosen vendor’s scores—demonstrating that these financial consulting services are not unique. To its credit, General Services did request that High‑Speed Rail provide a timeline of its plans to competitively bid this acquisition in the future.

General Services asserted that it approved the request because the vendor’s financial advisory services were crucial to ensuring that High-Speed Rail received timely delivery of funding. Although we do not question the importance of the services, General Services might have avoided this situation had it held the High-Speed Rail accountable in the past: this was the second time High-Speed Rail submitted a noncompetitive request for this contract, citing similar reasons. By approving this noncompetitive request that could have been competitively bid, General Services prevented other vendors from competing for this contract, potentially resulting in the State not receiving the best value.

Technology also approved a noncompetitive request for a fourth amendment that could have been competitively bid had it sufficiently planned and ensured that the vendor transferred its knowledge to the agency’s staff. In this instance, the Employment Development Department (EDD) entered into a $600,000 contract for work on its IT project to process unemployment insurance payments. In less than a year, EDD amended this contract three times for a total contract value of $8 million. Two of these three amendments involved noncompetitive requests that Technology approved. In its noncompetitive request for a fourth amendment—the item we tested—EDD stated that it wanted to extend the contract an additional year and add almost $2 million. EDD further stated that the vendor had expertise with the project and that EDD did not have staff with the technical skills necessary to perform the needed tasks. Finally, EDD stated that denying the request would negatively affect an IT project that allowed unemployed claimants to efficiently claim benefits.

However, in its approval of the request, Technology noted that the vendor had not met the contract’s knowledge transfer provision—the requirement that the vendor transfer to EDD staff the knowledge necessary to carry on the responsibilities that it performed without the vendor’s assistance. Moreover, in its previous requests to extend this contract, EDD acknowledged the importance of knowledge transfer, but Technology did not follow up to ensure that the agency took the steps necessary to avoid future noncompetitive requests. Instead, Technology approved the amendments, which increased the contract’s amount by more than 700 percent that may have been limited if EDD had been proactive in receiving timely knowledge transfer from its vendor. Although knowledge transfer is one of multiple reasons EDD cited for submitting the noncompetitive request, it repeatedly used this reason to justify the noncompetitive requests throughout the history of this contract. Technology staff agreed that it could strengthen its oversight by monitoring and following up with agencies that repeatedly submit inappropriate noncompetitive requests.

Both General Services and Technology Approved Noncompetitive Requests Without Ensuring That Agencies Adequately Justified the Contracts’ Prices or Identified Cost Savings

General Services and Technology approved 14 of the 27 noncompetitive requests we reviewed despite the agencies’ failure to adequately justify the prices of the contracts and amendments were fair and reasonable, as the noncompetitive request form requires. For several of these requests, agencies compared the vendors’ proposed rates to their rates in the original contracts, sometimes adjusting for inflation. However, in some cases, a number of years had elapsed since the agencies entered the original contracts and it is reasonable to expect that agencies would include comparisons to similar vendors in the current market. Furthermore, we found that General Services and Technology approved noncompetitive requests in which agencies did not demonstrate any cost savings or costs avoided.

For example, in 2014 Technology’s Acquisitions and IT Program Management unit, which is responsible for acquiring goods and services for Technology, submitted a noncompetitive request for website services.2 In its price justification, this Technology unit compared the vendor’s proposed hourly rates to the rates in the vendor’s prior competitive bid related to these services from 2007, adjusted with a 3 percent annual increase for inflation. However, we question the validity of this methodology given that seven years had elapsed and significant changes had occurred in the economy. Had this Technology unit provided a valid price analysis that, for example, compared the vendor’s rates to rates for similar services included in the State’s master agreements, that analysis would have revealed that the vendor’s rates in this particular contract were significantly higher than its rates in other state contracts.3 For instance, this Technology unit’s price comparison established the vendor’s rate for a project manager position as $195 an hour. However, the same vendor’s listed rate for the project manager position in the comparable statewide master agreement was $160 an hour. In fact, the master agreement’s rate for a higher-level senior project manager position was only $180 an hour. We also noted that other vendors offered much lower rates for similar positions in the State’s master agreements. An assistant deputy director for Technology acknowledged that this should not have occurred. However, the assistant deputy director stated that a fair price is one factor, among many, that Technology considers when reviewing noncompetitive requests. While this may be true, by not requiring agencies to substantiate fair prices before approving a request, General Services and Technology cannot ensure that the State is receiving the best value for goods and services.

Moreover, in 12 of the 27 noncompetitive requests General Services and Technology approved, agencies did not adequately demonstrate cost savings or costs avoided as required on the noncompetitive request justification form. For instance, in its noncompetitive request for an amendment, the Department of Consumer Affairs (Consumer Affairs) simply asserted to Technology in its justification for cost savings that using a noncompetitive contract would enable the State to avoid interruptions and the costs of procuring a new vendor to work on the BreEZe system, Consumer Affairs’ computerized licensing and enforcement system. Although this may have been true, the agency’s brief statement that entering a noncompetitive request amendment would allow the State to avoid the normal costs of procurement is not sufficient to quantify or justify the costs avoided. Further, this same inadequate justification could be used by any state agency wishing to justify this aspect of the noncompetitive request. Consumer Affairs’ failure to adequately justify the cost savings of this amendment is particularly concerning given that it increased the existing contract’s cost by about 60 percent, or $5.6 million over a one-year period. To conform with best practices, we expected Consumer Affairs to quantify dollar amounts of the avoided costs and to provide the underlying support. Technology agreed that it should require agencies to quantify possible cost savings or costs avoided before approving noncompetitive requests. Without such information, General Services and Technology cannot ensure that the benefits of the State’s noncompetitive procurements outweigh the costs.

General Services’ and Technology’s Available Enforcement Mechanisms for Responding to Agencies’ Noncompliance With Contracting Practices

Formal Mechanisms:

  • Reject contracts subject to General Services’ and Technology’s approval.
  • Refuse or revoke agencies’ requests for exemptions to purchase up to $150,000 for non-IT services acquisitions without General Services’ oversight. (General Services only)
  • Deny noncompetitive requests. (General Services and Technology)
  • Reduce or revoke agencies’ delegated purchasing authorities. (General Services only) However, Technology has the authority to establish restrictions or controls to reduce or revoke agencies’ authority to acquire information technology or telecommunications goods or services.
  • Deny agencies’ requests for one-time increases to make procurements over their purchasing thresholds that they plan to purchase themselves. (General Services only)

Cautionary Mechanisms:

  • Issue a warning in the approval letter to agencies that no additional noncompetitive requests will be approved. (General Services and Technology)
  • Require agencies to submit corrective action plans when they submit noncompetitive requests caused by insufficient time to solicit bids. (General Services and Technology)

Sources: State law, the State Contracting Manual, General Services’ policies and procurement documents, and Technology’s practices.

Similarly, we also noted that agencies provided scarce documentation of fair and reasonable price justifications for their non-IT service contracts that did not involve noncompetitive requests but that state laws or policies exempted from competition for other reasons. These contracts were generally exempt because they involved the procurement of legal services, services related to government aid or local assistance, or services covered under other statutory exemptions. We found that the agencies that submitted these contracts for approval often stated that prices were fair and reasonable but did not provide any evidence to support such claims. For example, the California Department of Corrections and Rehabilitation (Corrections) developed a contract with a law firm for $1.5 million for legal services. In its price justification, Corrections asserted that the hourly rates the law firm charged for its services were consistent with other current legal service contracts with similar experience and expertise; however, it did not provide any documentation of the rate comparison. When we questioned General Services’ Legal Services about the lack of documentation we noted in some contracts exempt from competition, staff stated they did not have enough specific expertise to identify reasonable rates for every field, and thus they rely on the judgment of the agencies submitting the contracts. However, the lack of documentation demonstrating cost analyses for fair and reasonable pricing reduces transparency and raises questions about whether the rates the agencies obtained were the best value for the State.

General Services and Technology Have Rarely Used Their Enforcement Authority to Ensure That State Agencies Engage in Appropriate Noncompetitive Contracting Practices

Although General Services and Technology have enforcement mechanisms they can use for agencies that do not comply with the State’s noncompetitive procurement policies, we found that they rarely employed those mechanisms during our five-year audit period covering fiscal years 2011–12 through 2015–16. General Services in particular has a number of different enforcement mechanisms, both formal and cautionary, available to its various units, as the text box shows. Although Technology cannot reduce agencies’ delegated purchasing authority, it does have the ability to take steps such as issuing warning letters and requiring agencies to submit corrective action plans. Table 7 identifies the enforcement mechanisms General Services and Technology used or did not use in response to the nine noncompetitive requests we believe agencies could have avoided. Had General Services and Technology used their enforcement authority in these instances, they might have prevented or minimized the agencies’ use of noncompetitive requests.

Despite their respective enforcement authority, General Services and Technology did not consistently use the mechanisms available to them. For example, although both General Services and Technology can deny an agency’s noncompetitive request, General Services indicated it did so only five times for noncompetitive requests over $1 million during our audit period and Technology told us it had never formally denied any agency’s noncompetitive request since it became responsible for procurements related to reportable IT projects and telecommunications services in July 2013. Both General Services and Technology indicated that generally they did not deny noncompetitive requests because doing so could impact essential state services.

Table 7
General Services and Technology Did Not Use Enforcement Mechanisms for Noncompetitive Requests That Could Have Been Competitively Bid
(in Millions)

Contracting Agency Name Reason for Noncompetitive Request Contract or Amendment Dollar Value of contract or amendment we evaluated Oversight Entity Reduced or Revoked Purchasing Authority or Removed Purchasing Authority Exemption Related to This Request Agency Submitted Corrective Action Plan Oversight Entity Monitored Corrective Action Plan Oversight Entity told agency it would not approve additional noncompetitive Requests In Its Approval Letter Oversight Entity Denied a Repeat Noncompetitive Request
General Services' Oversight Health Care Services Extension and increase of cost for Medi-Cal dental program contract. Seventh Amendment $835 X X X NA*
DMV Extension and increase of cost for updating the driver’s license card production system currently experiencing technical issues. Fifth Amendment 75.5 X X NA X X
High-Speed Rail Extension and increase of cost for financial consulting services. Second Amendment 3 X X X§
Department of Forestry and Fire Protection Extension and increase of cost for Cal Fire aviation services. Fourth Amendment 27.8 X X X NA*
CPUC Extension and increase of cost for California Lifeline program. Sixth Amendment 6.9 X X X X
Technology's Oversight Department of Fish and Wildlife Continued maintenance and operations for automated licensing system.II Original Contract $28.9 NA** X X NAII
EDD Extension and increase of cost for additional needs/staff to support the unemployment benefits system. Needed vendor staff because EDD staff was not trained to carry out vendor’s responsibilities. Fourth Amendment 2 NA** X X
DMV Extension and increase of cost for more self‑service terminals. Ninth Amendment 18.6 NA** X X
Secretary of State Extension of project management services for the statewide voter database.II Original Contract 2.3 NA** X X NAII

Sources: California State Auditor’s analysis of General Services’ and Technology’s procurement files.

Note: The results are based on the criteria that General Services uses and Technology follows to assess the appropriateness of noncompetitive bids. Contracts appear in the table if the requesting agency did not substantiate that it met certain criteria to justify a noncompetitive request.

NA = Not applicable.

= Met the requirement.

X = Did not meet the requirement.

* The agency did not submit a noncompetitive request for the amendment preceding the item we evaluated.

Although DMV did not fill out a corrective action plan and General Services did not require it to submit one, we determined that the corrective action plan should have been required.

General Services reduced High Speed Rail’s purchasing authority levels unrelated to this request and acquisition type.

§ Subsequent to the test item, General Services approved a third amendment for a three-month extension at no additional cost before High-Speed Rail released a request for proposal in May 2014.

II Similar to an amendment, these contracts continue services with the same vendor but under a new contract.

** Technology does not have the authority to reduce or revoke an agency’s delegated purchasing authority.

General Services also rarely reduced or revoked agencies’ purchasing thresholds, although this is one of its key means of enforcement. We use the term purchasing threshold to encompass the purchasing authority levels granted by the Purchasing Authority unit for all non-IT goods or IT goods and services and the special exemption to purchase up to $150,000 for non-IT services contracts without Legal Services’ approval. General Services indicates in its noncompetitive request form that reducing or revoking purchasing authority can be a penalty for noncompliance. When General Services revokes an agency’s purchasing authority, that agency must generally submit all its goods acquisitions to General Services for processing, regardless of dollar amount. Nonetheless, according to a section manager for General Services’ Purchasing Authority unit, it did not use this enforcement mechanism to combat any of the inappropriate noncompetitive requests we identified although it did so twice for other reasons during our audit period, unrelated to the items we reviewed. For example, although General Services reduced High-Speed Rail’s purchasing authority in 2012, it asserted that it took this action not because of High-Speed Rail’s noncompetitive requests but rather because the agency lacked sufficiently trained procurement staff, faced challenges in conducting high-quality acquisitions, and did not comply with General Services’ policies. The section manager for General Services’ Purchasing Authority unit said that reducing purchasing authority is only appropriate when an agency displays poor contract management while purchasing within its authority. Further, she asserted that reducing an agency’s purchasing authority does not solve poor contract management related to a contract that was procured above an agency’s purchasing authority and therefore already required General Services’ approval. However, we question why General Services would limit its use of this mechanism to procurements under an agency’s purchasing authority, which is generally $1 million or less. Increased use of this mechanism in appropriate situations of poor contract management would provide General Services significant leverage to hold agencies accountable.

Further, neither General Services nor Technology has monitored agencies’ corrective action plans to ensure that the agencies’ future use of noncompetitive requests is appropriate. The noncompetitive request form requires agencies to submit corrective action plans when the noncompetitive requests could have been competitively bid but were not because of insufficient time to complete the competitive acquisition process. This corrective action plan requires agencies to explain how they will avoid using noncompetitive requests that should have been competitively bid in the future. Although agencies are to include corrective action plans with their noncompetitive requests when they meet this requirement, General Services and Technology should also follow up with agencies when these plans are required but have not been submitted. The corrective action plan form states: “Failure to follow the corrective action plan may result in the loss of your department’s delegated procurement authority. This plan must be kept on file for future auditing purposes.” However, we discovered that none of the units within General Services or Technology monitor or follow up with agencies when corrective action plans are required or “audit” those agencies’ implementation of corrective action plans. As a result, agencies did not always adhere to their corrective action plans.

A noncompetitive request submitted by the Department of Health Care Services (Health Care Services) illustrates why monitoring corrective action plans is critical. Specifically, in 2013 Health Care Services requested approval of a noncompetitive request for an $835 million amendment to its contract for administrative services for its Medi-Cal dental program—the seventh such amendment in the contract’s history. Because Health Care Services cited insufficient time to complete the competitive acquisition process as a reason for the noncompetitive request, it included with its noncompetitive request a corrective action plan with a proposed timeline for soliciting competition in the future. However, General Services, which approved the request, did not monitor Health Care Services to determine if it followed this timeline. In fact, when we asked General Services whether Health Care Services had followed its corrective action plan, General Services had to contact the agency to determine the plan’s status. Although Health Care Services did release a request for proposal for these services, it only did so 18 months after the date stated in the timeline in its corrective action plan, which further delayed the opportunity for competition. We are concerned that General Services did not follow up regarding an amendment worth $835 million. Further, we question the usefulness of corrective action plans if General Services and Technology do not provide oversight of their implementation, leaving agencies with little incentive to follow them.

Both oversight entities provided reasons for why they do not track or follow up on corrective action plans. An analyst with General Services stated that it had not formally monitored corrective action plans since 2011 because, due to limited resources, analysts only monitor agencies’ corrective action plans when they notice an abusive pattern of noncompetitive requests. According to the analyst, General Services has not noticed any specific agencies abusing the noncompetitive request process since that time. However, as the example involving Health Care Services demonstrates, we found that agencies did not always adhere to their corrective action plans, which suggests that increased monitoring is necessary. General Services agreed that increased monitoring of corrective action plans would be beneficial. A former branch chief with Technology stated that it does not have a formal process for monitoring corrective action plans and that contract management is the responsibility of individual agencies. Furthermore, he stated that Technology relies on General Services to ensure agencies’ compliance with the state’s procurement policies. Although General Services does verify agencies’ compliance with state contracting policies, this does not absolve Technology of its responsibility to monitor the corrective action plans it receives. Technology agreed that monitoring corrective action plans could improve its oversight of agencies’ use of noncompetitive requests.

Although General Services and Technology can both use warning letters—a warning provided in the approval letter that no additional noncompetitive requests will be approved—as another mechanism to oversee agencies’ use of noncompetitive requests, they did not always use them or, when they did, did not consistently follow through on the contents of the letters. Specifically, we found cases when General Services could have issued such warning letters to agencies but did not. For example, General Services did not issue a warning letter even after the CPUC repeatedly failed to sufficiently plan to avoid using noncompetitive requests, as we discussed earlier in this chapter. General Services asserted that it will draft a process for determining when to issue warning letters to high‑level executive staff in the agencies making the procurements.

Moreover, we found instances in which General Services and Technology issued such letters yet approved subsequent noncompetitive requests from the same agencies. A contract involving the Department of Motor Vehicles (DMV) demonstrates that the use of the warning letters may be unsuccessful if the oversight entities do not enforce the warnings. In this instance, DMV had already amended its contract with a vendor for self‑service terminals seven times using either noncompetitive requests or another exemption type. When Technology approved the eighth such amendment—adding $7.1 million and 18 months to the existing $8.1 million contract—it warned DMV that it would not approve any further noncompetitive requests related to this contract. However, Technology then approved DMV’s noncompetitive request for a ninth amendment, adding an additional three years and $18.6 million to the contract. Technology staff indicated that it approved this ninth amendment because DMV had identified additional technologies that it wished to explore for its future procurement. However, Technology had already granted DMV the eighth amendment for 18 months to allow for time to conduct a competitive procurement.

Because General Services and Technology did not consistently use their enforcement authority, they allowed agencies to continue to inappropriately use noncompetitive requests. By applying their enforcement mechanisms more consistently, General Services and Technology could promote accountability and prevent agencies from taking advantage of the noncompetitive request process. To ensure that this occurs, we believe the Legislature should require General Services and Technology to report all noncompetitive requests they approve over $1 million along with any enforcement actions they take against the agencies making the noncompetitive requests. In addition to increasing the agencies’ accountability, this report to the Legislature could provide another means of offering transparency to the public regarding agencies that do not engage in competitive bidding. We believe this increased transparency is particularly important given that neither General Services nor Technology has yet to use either SCPRS or FI$Cal for this purpose, as we describe in Chapter 1.

In addition, General Services should implement a formal escalation process for agencies that repeatedly take advantage of the noncompetitive request process. General Services could begin by issuing a warning letter, followed by potentially reducing or revoking the agency’s purchasing threshold for specific types of acquisitions—for example, for IT services only. Finally, it could reduce or revoke the agency’s purchasing authority for other acquisition types in egregious examples of noncompliance. General Services does not agree with all aspects of this approach. Specifically, the section manager of the Procurement Division asserted that it seeks to apply consequences—such as reducing or revoking an agency’s purchasing threshold—that it believes relate to the specific problem it has identified. She stated that, for instance, it would not make sense to reduce the purchasing threshold for IT procurements if the noncompetitive request involved the non-IT services contracting area; in such a case, the consequence would not relate to the offense. However, as we have shown, General Services’ current approach to enforcement has not consistently deterred agencies from taking advantage of noncompetitive requests. Therefore, it should use an escalating approach that takes advantage of its other mechanisms—including issuing warning letters to agency executives and reducing purchasing thresholds in scenarios of continuous noncompliance to ensure that the consequences align with the degree to which agencies poorly manage their contracts management.

Recommendations

Legislature

To promote accountability for and transparency of the State’s noncompetitive request process, the Legislature should require General Services and Technology to submit an annual report of all noncompetitive requests they approve with values over $1 million. This report should include performance metrics such as the percentage of procurement dollars approved as noncompetitive requests. This could be a published annual report or the two agencies could provide this information publicly on their websites. In addition, the Legislature could require agencies to publicly justify their noncompetitive requests in Legislative hearings when it sees fit. For each noncompetitive request listed in the annual report, General Services and Technology should include—at a minimum—the following information:

General Services

To clarify the allowable reasons for using noncompetitive requests and to ensure that agencies understand these reasons, General Services should, within 180 days, enhance the criteria in the State Contracting Manual to include examples of appropriate and inappropriate circumstances related to justifying a noncompetitive request. In particular, it should clearly reiterate that poor contract planning is not a sufficient justification for a noncompetitive request for all acquisition types. Further, General Services should develop specific criteria for what constitutes an appropriate noncompetitive request for non-IT services acquisitions. General Services should notify all agencies of the clarifications in the State Contracting Manual and should reiterate that all noncompetitive requests must meet the enhanced criteria.

To ensure that the State receives the best value for its contracts, General Services should immediately begin performing the following:

To ensure that it holds agencies accountable for implementing the corrective action plans that they submit with noncompetitive requests, General Services should immediately begin tracking all outstanding plans and following up to ensure that agencies complete them. For example, General Services should require an agency to include key dates in its corrective action plan that the agency plans to meet to conduct a competitive procurement and report its progress to General Services. Further, General Services should inquire about the steps that agencies have taken before the contract expiration dates in their most recent noncompetitive requests.

To ensure that it consistently and appropriately responds when agencies fail to justify their noncompetitive requests, plan sufficiently to avoid the noncompetitive process, or follow their corrective action plans, General Services should create an escalation process within 90 days that outlines the order and severity of enforcement mechanisms it will use. The mechanisms it applies should escalate according to the number or severity of offenses it identifies. For example, General Services could begin by sending a warning letter to high-level agency executives, followed by reducing or revoking an agency’s purchasing threshold for specific types of acquisitions—for example, IT services—and finally by reducing or revoking an agency’s purchasing threshold for all acquisition types in scenarios of repetitive noncompliance.

Technology

To ensure that the State receives the best value for its noncompetitive requests, Technology should immediately begin to require that agencies justify that the price is fair and reasonable. This should include a current price analysis pointing to competitive pricing from another contract, such as a statewide agreement, or a comparison of rates to other available vendors, or another valid price analysis with objective evidence. Further, Technology should require agencies to quantify and substantiate their cost savings or averted costs.

To ensure that it holds agencies accountable for implementing the corrective action plans that they submit with noncompetitive requests, Technology should immediately begin tracking all outstanding corrective action plans and following up to ensure that agencies complete them. For example, Technology should require that an agency include key dates in its corrective action plan that the agency plans to meet to conduct a competitive procurement and report its progress to Technology. Further, Technology should inquire about the steps that agencies have taken before the contract expiration dates in their most recent noncompetitive requests.

To ensure that agencies do not repeatedly submit inappropriate noncompetitive requests after receiving a warning, Technology should track and follow up on instances in which it has issued a warning letter. Further, when appropriate, Technology should follow through with the consequences it includes in its warning letters.


We conducted this audit under the authority vested in the California State Auditor by Section 8543 et seq. of the California Government Code and according to generally accepted government auditing standards. Those standards require that we plan and perform the audit to obtain sufficient, appropriate evidence to provide a reasonable basis for our findings and conclusions based on our audit objectives specified in the Scope and Methodology section of the report. We believe that the evidence obtained provides a reasonable basis for our findings and conclusions based on our audit objectives.

Respectfully submitted,

ELAINE M. HOWLE, CPA
State Auditor


Date:
June 20, 2017

Staff:
Nicholas Kolitsos, CPA, Audit Principal
Michelle J. Sanders
Brigid Drury, MPAc
Forrest Flanagan
Hunter Wang, CFE

IT Audits:
Michelle J. Baur, CISA, Audit Principal
Lindsay Harris, MBA, CISA
Richard W. Fry, MPA, ACDA
Jesse R. Walden

Legal Counsel:
Joseph L. Porche, Staff Counsel

For questions regarding the contents of this report, please contact
Margarita Fernández, Chief of Public Affairs, at 916.445.0255.




Footnotes

2 For acquisitions Technology conducts itself, its Acquisitions and IT Program Management unit is responsible for procuring goods and services. If it needs approval for acquisitions related to reportable IT projects, Technology’s Procurement Division approves the acquisition. Go back to text

3 Master agreements are contracts that General Services awards competitively and makes available to any public entity. These types of agreements establish prequalified lists of vendors and simplify the purchasing process for the agencies. Go back to text



Back to top